Allowability of Costs
In this section
Allowability of Costs
Office Of Management And Budget-uniform Administrative Requirements, Cost Principles, And Audit Requirements, For Federal Awards.
This final guidance supersedes and streamlines requirements from OMB circulars a–21, a–87, a–110, and a–122 (which have been placed in OMB guidances); circulars a–89, a–102, and a–133; and the guidance in circular a–50 on single audit act follow-up. future reform efforts may eventually seek to incorporate the cost principles for hospitals in department of health and human services regulations. copies of the OMB circulars that are superseded by this guidance are available on omb’s web site at https://obamawhitehouse.archives.gov/omb/circulars_default/. the final guidance consolidates the guidance previously contained in the aforementioned citations into a streamlined form that aims to improve both the clarity and accessibility. this final guidance is located in title 2 of the code of federal regulations.
Applicability Date: This guidance is applicable for Federal agencies December 26, 2013 and applicable for non-Federal entities as described in this guidance
§ 200.110 Effective/applicability date
(a) The standards set forth in this Part which affect administration of Federal awards issued by Federal agencies become effective once implemented by Federal agencies or when any future amendment to this Part becomes final. Federal agencies must implement the policies and procedures applicable to Federal awards by promulgating a regulation to be effective by December 26, 2014 unless different provisions are required by statute or approved by OMB.
(b) The standards set forth in Subpart F—Audit Requirements of this Part and any other standards which apply directly to Federal agencies will be effective December 26, 2013 and will apply to audits of fiscal years beginning on or after December 26, 2014
§ 200.413 Direct costs
(a) General. Direct costs are those costs that can be identified specifically with a particular final cost objective, such as a Federal award, or other internally or externally funded activity, or that can be directly assigned to such activities relatively easily with a high degree of accuracy. Costs incurred for the same purpose in like circumstances must be treated consistently as either direct or indirect (F&A) costs. See also § 200.405 Allocable costs.
(b) Application to Federal awards. Identification with the Federal award rather than the nature of the goods and services involved is the determining factor in distinguishing direct from indirect (F&A) costs of Federal awards. Typical costs charged directly to a Federal award are the compensation of employees who work on that award, their related fringe benefit costs, the costs of materials and other items of expense incurred for the Federal award. If directly related to a specific award, certain costs that otherwise would be treated as indirect costs may also include extraordinary utility consumption, the cost of materials supplied from stock or services rendered by specialized facilities or other institutional service operations.
(c) The salaries of administrative and clerical staff should normally be treated as indirect (F&A) costs. Direct charging of these costs may be appropriate only if all of the following conditions are met:
(1) Administrative or clerical services are integral to a project or activity;
(2) Individuals involved can be specifically identified with the project or activity;
(3) Such costs are explicitly included in the budget or have the prior written approval of the Federal awarding agency; and
(4) The costs are not also recovered as indirect costs.
(d) Minor items. Any direct cost of minor amount may be treated as an indirect (F&A) cost for reasons of practicality where such accounting treatment for that item of cost is consistently applied to all Federal and non-Federal cost objectives.
§ 200.414 Indirect (F&A) costs
(a) Facilities and Administration Classification. For major Institutions of Higher Education (IHEs) and major nonprofit organizations, indirect (F&A) costs must be classified within two broad categories: "Facilities" and "Administration." "Facilities" is defined as depreciation on buildings, equipment and capital improvement, interest on debt associated with certain buildings, equipment and capital improvements, and operations and maintenance expenses. "Administration" is defined as general administration and general expenses such as the director’s office, accounting, personnel and all other types of expenditures not listed specifically under one of the subcategories of "Facilities" (including cross allocations from other pools, where applicable). For nonprofit organizations, library expenses are included in the "Administration" category; for institutions of higher education, they are included in the "Facilities" category. Major IHEs are defined as those required to use the Standard Format for Submission as noted in Appendix III to Part 200—Indirect (F&A) Costs Identification and Assignment, and Rate Determination for Institutions of Higher Education (IHEs) paragraph C. 11. Major nonprofit organizations are those which receive more than $10 million dollars in direct Federal funding.
General Provisions for Selected Items of Cost
§ 200.420 Considerations for selected items of cost
This section provides principles to be applied in establishing the allowability of certain items involved in determining cost, in addition to the requirements of Subtitle II. Basic Considerations of this subpart. These principles apply whether or not a particular item of cost is properly treated as direct cost or indirect (F&A) cost. Failure to mention a particular item of cost is not intended to imply that it is either allowable or unallowable; rather, determination as to allowability in each case should be based on the treatment provided for similar or related items of cost, and based on the principles described in § 200.402 Composition of costs through 200.411 Adjustment of previously negotiated indirect (F&A) cost rates containing unallowable costs. In case of a discrepancy between the provisions of a specific Federal award and the provisions below, the Federal award governs. Criteria outlined in § 200.403 Factors affecting allowability of cost must be applied in determining allowability. See also § 200.102 Exceptions.
§ 200.453 Materials and supplies costs, including costs of computing devices
(a) Costs incurred for materials, supplies, and fabricated parts necessary to carry out a Federal award are allowable.
(b) Purchased materials and supplies must be charged at their actual prices, net of applicable credits. Withdrawals from general stores or stockrooms should be charged at their actual net cost under any recognized method of pricing inventory withdrawals, consistently applied. Incoming transportation charges are a proper part of materials and supplies costs.
(c) Materials and supplies used for the performance of a Federal award may be charged as direct costs. In the specific case of computing devices, charging as direct costs is allowable for devices that are essential and allocable, but not solely dedicated, to the performance of a Federal award.
(d) Where federally-donated or furnished materials are used in performing the Federal award, such materials will be used without charge.